5.0
★★★★★ Read our reviews on Google
Can a Builder Move or Disconnect Gas Pipework During Refurbishment?

Can a Builder Move or Disconnect Gas Pipework During Refurbishment?

Short answer: no. Moving, capping, cutting or disconnecting gas pipework, appliances or flues is gas work. Under the Gas Safety (Installation and Use) Regulations 1998 it must be done by a competent engineer from a Gas Safe registered business, registered for that type of work. A builder who finds gas services in the way should stop, and the programme should be changed around a specialist alteration.

Refurbishment work often exposes services that were not obvious at tender stage. When gas pipework, appliances or flues conflict with an extension, alteration or strip-out, they are easy to treat as just another obstruction. That is where things go wrong.

Why is HSE warning about illegal gas work?

During Gas Safety Week (14 to 20 September 2026), HSE reported that 17 people had been convicted for carrying out gas work illegally since the beginning of 2025. Unregistered gas work can lead to leaks, fires, explosions and carbon monoxide poisoning.

HSE’s September 2026 warning matters to refurbishment contractors because gas risks can arise during ordinary building work, even when the job was never described as a gas installation.

A separate HSE prosecution reported in August involved an extension built over existing gas service pipework and around a boiler flue, without the required alterations being made. The installation was later classified as immediately dangerous.

What does Regulation 3 require?

Regulation 3 of the Gas Safety (Installation and Use) Regulations 1998 requires gas work to be carried out by competent people. Where a business does the work, it must be a member of the class of persons approved by HSE, which in practice means the Gas Safe Register.

Registration is not a blanket licence. The engineer should be competent and registered for the particular type of gas work involved. For a general builder, the rule is simple: if the gas installation needs changing, it is not your trade’s job.

How can building work create a gas risk?

It goes well beyond boiler installation. Excavation can expose service pipes. Structural alterations can affect flue routes. Kitchen or plant-room changes can clash with existing pipework. New walls can enclose equipment, and demolition can remove supports or ventilation that formed part of the original safe installation.

This is a CDM 2015 issue as much as a gas one. Foreseeable risks should be planned and coordinated, not left for workers to solve at the point of work. Existing-services information, surveys, pre-construction information and site briefings all help find the problem early. If the method changes once a service is found, the risk assessment needs reviewing too.

Who controls the interface on site?

On projects with several contractors, the principal contractor must plan, manage, monitor and coordinate the construction phase. That does not make them a gas specialist, but they should decide who is authorised to do the gas work and how it fits the sequence. We cover this in more detail in Can a principal contractor leave safety to subcontractors?

Make the boundary explicit in the RAMS and construction phase plan. General operatives may expose an area carefully under an agreed method, but any intervention in the gas installation itself belongs to the registered engineer, with isolation, testing and handover clearly defined.

Check registration as well. HSE has prosecuted cases where businesses relied on people who claimed to be qualified but were not. Looking up the engineer or business on the Gas Safe Register takes a minute and should be done before the work starts.

What should happen when gas services are in the way?

Stop the affected activity and establish what the service is, whether it is live and what change is actually needed. Do not cut, cap, bend, reroute or disconnect pipework to keep progress going.

Give the gas engineer enough information to understand the finished building, not just today’s obstruction. Flue routes, ventilation, maintenance access, protection from damage and new structural or fire-resisting elements may all need considering.

What should you do now?

  • Identify existing gas services, appliances and flues during pre-start planning.
  • Make the boundary between general building work and gas work clear in RAMS and briefings.
  • Do not let builders or other trades move, disconnect or modify gas installations.
  • Check the engineer or business on the Gas Safe Register before work starts.
  • Coordinate isolation, alteration, testing and reinstatement with the programme.
  • Stop and reassess when unexpected pipework or flues are found.
  • Record service changes so the handover information matches what was actually left in place.

Our professional view

Most gas-safety failures we hear about on refurbishment jobs start as coordination failures, not deliberate law-breaking. A service is found late, the programme is tight and someone makes a quick alteration to keep moving. Clear stop-work boundaries and early specialist involvement are far more reliable than expecting operatives to judge the limit themselves.

All Star Safety Ltd’s CDM 2015 Awareness course covers dutyholder responsibilities and construction-phase coordination. For supervisors who manage these interfaces day to day, the Level 4 NVQ in Construction Site Supervision builds and evidences that competence on your own site. If you would like a second pair of eyes on your RAMS or construction phase plan, talk to our health and safety consultancy team on 01473 561402.

What Should Construction Sites Review When the Clocks Go Back?

What Should Construction Sites Review When the Clocks Go Back?

When the UK clocks move back, construction sites lose useful daylight at exactly the time many projects are still working through busy afternoon periods. The change should trigger more than a reminder about watches and vehicle clocks: site lighting, pedestrian routes, plant movements, access, emergency arrangements and supervision may all need reviewing.

Shorter daylight immediately changes familiar site risks

GOV.UK lists Sunday 25 October 2026 as the date the UK clocks go back by one hour, returning from British Summer Time to Greenwich Mean Time. The practical consequence for construction is earlier darkness through late autumn and winter while tasks, deliveries and vehicle movements may continue on the same working programme.

The practical risk is that a site can look unchanged on paper while visibility has altered significantly. A pedestrian route that was comfortably visible at 4.30pm earlier in the month may now sit in shadow, and a loading area that relied partly on daylight may need artificial lighting for routine operations.

GOV.UK confirms the 2026 clock change date. For construction managers, the useful response is to treat it as a seasonal review point: walk the site at the times work will actually take place and check whether existing controls still perform as intended.

Lighting is a legal site requirement, not a seasonal extra

Regulation 35 of the Construction (Design and Management) Regulations 2015 requires each construction site, together with its approaches and traffic routes, to have suitable and sufficient lighting. So far as reasonably practicable, that lighting should be natural, but artificial lighting is required where natural light is inadequate.

The regulation also requires artificial lighting not to adversely affect the perception of safety signs or signals. Where failure of the main artificial lighting could create a health or safety risk, suitable and sufficient secondary lighting must be provided. Those are legal requirements, rather than optional seasonal good practice.

HSE’s construction lighting guidance adds practical detail. It highlights the need to avoid shadows that hide hazards, maintain visibility of safety equipment and escape routes, and provide emergency lighting where a primary lighting failure could leave people exposed to danger.

Traffic routes and pedestrian interfaces need another look

Reduced daylight is especially significant where people and vehicles interact. Reversing areas, gate entrances, loading zones, crossings, turning points and routes beside hoarding can become harder to read when contrast falls, glare increases or temporary lighting illuminates one area well while leaving another unexpectedly dark.

HSE’s workplace transport guidance says roads, manoeuvring areas and yards should be sufficiently lit, with particular attention to junctions, plant, buildings, pedestrian areas and loading or unloading locations. It also warns that lighting should be positioned to reduce glare and shadows.

A useful site check is to walk the normal pedestrian route while plant is operating, rather than inspecting lighting from the site office or from a stationary vehicle. Ask whether a driver can distinguish a person from the background, whether signs remain legible and whether banksmen can see the full movement area.

Temporary lighting can create new hazards if poorly arranged

Adding more lights is not automatically the answer. Poorly positioned floodlights can create glare for drivers, deep shadows behind materials, confusing reflections or significant changes in brightness between internal and external areas. Temporary supplies, trailing cables and generators can also introduce electrical, access and housekeeping risks if they are added reactively.

The arrangement should therefore be planned around the work. Lighting needs to reach the task, access and travel routes without obscuring hazards or changing the appearance of safety signs. Where work moves regularly, such as external groundworks or façade activities, the lighting plan may need to move with it rather than remain fixed.

Inspections and emergency arrangements should reflect darker hours

Lighting equipment also needs maintaining. A failed lamp, damaged cable or moved tower can undermine an otherwise sensible arrangement, so routine inspections should include the condition and position of temporary lighting. The timing matters: a lighting check completed at midday cannot demonstrate that the site remains suitable after sunset.

Emergency arrangements deserve the same review. If workers would need to descend scaffold access, cross an excavation area or navigate an enclosed structure following a power failure, managers should consider what secondary lighting is necessary. Escape routes should remain identifiable and usable even when normal site lighting is unavailable.

What should you do now?

  • Walk the site during the actual darker working period, not only in daylight.
  • Check access routes, stairs, scaffold approaches, welfare routes and loading areas for shadows or dark spots.
  • Review vehicle and pedestrian interfaces, particularly reversing areas, junctions and crossings.
  • Confirm artificial lighting does not create glare or obscure safety signs and signals.
  • Check temporary lighting equipment, cables, generators and supports for condition and safe positioning.
  • Verify secondary or emergency lighting where failure of the main supply could create a safety risk.
  • Update RAMS, traffic plans or site arrangements where the seasonal change materially alters the controls.

Our professional view

The clocks changing is useful because it creates a predictable review point. The risk is not the clock itself; it is continuing to operate a site on assumptions formed when visibility was better. A short inspection at the right time of day can reveal issues that are invisible during a normal morning management walk.

Businesses that want an independent check of site arrangements, traffic management, RAMS or wider seasonal controls can use All Star Safety’s health and safety consultancy service for practical site-based support.

Why a Safety Data Sheet Is Not Your COSHH Assessment

Why a Safety Data Sheet Is Not Your COSHH Assessment

Safety data sheets are essential sources of chemical information, but HSE is explicit that an SDS is not a COSHH risk assessment. Construction businesses need to translate product information into the reality of the task: how the substance is used, who can be exposed, what the exposure routes are and which controls will work in the actual workplace.

The supplier document answers a different question

HSE’s guidance on chemical safety data sheets explains that an SDS describes the hazards presented by a chemical and provides information on matters such as handling, storage and emergency measures. It is valuable input to assessment, but it does not assess your particular task.

HSE states this plainly: a safety data sheet is not a risk assessment. The employer still needs to consider the way the substance is used in its own workplace and the likelihood, route, duration and level of exposure.

A folder containing current SDSs can therefore be good chemical-management housekeeping while still leaving a significant gap in the COSHH process.

Construction creates hazardous substances as well as buying them

One reason SDS-led assessments can fail is that not every hazardous substance arrives in a container with a label. HSE’s COSHH assessment guidance reminds employers to consider substances generated by work processes, including wood dust from sanding, silica-containing dust from cutting and fumes from welding.

If the assessment inventory contains only purchased paints, adhesives and cleaners, it may miss some of the most important occupational-health exposures created by the work itself.

The task assessment should therefore begin with the activity as well as the product list: what is cut, drilled, mixed, sprayed, welded, sanded, cleaned or applied, and what does that process put into the air or onto the skin?

Exposure route changes the control strategy

The same substance can create different risks depending on how exposure occurs. Workers may inhale dust, mist, vapour, fume or gas; substances can contact or pass through the skin; contaminated hands can create ingestion risks.

That matters because an SDS statement such as “wear protective gloves” is not enough to select a suitable control system. The assessment needs to consider the actual concentration, duration, method of application, ventilation, number of workers and potential for spread to other people.

For a small adhesive application, suitable gloves and ventilation may form part of the control. Spray application or use in a confined area could create a very different exposure profile requiring a more substantial approach.

Control should follow the hierarchy, not start with PPE

COSHH requires exposure to be prevented where reasonably practicable and adequately controlled where prevention is not possible. The assessment should therefore consider whether the substance or process can be eliminated or substituted before relying on PPE.

Engineering and process controls may include local exhaust ventilation, enclosed application, water suppression, on-tool extraction, changes in product form or restricting the amount used. PPE and RPE can be important, but they depend on correct selection, fit, use, maintenance and supervision.

The most visible control is not necessarily the most effective one. A worker wearing a mask while producing uncontrolled dust may look protected while the wider work area remains contaminated.

The assessment must be usable by the people doing the work

A good COSHH assessment should tell the supervisor and worker what matters for the specific job: the harmful substance, exposure route, required controls, PPE or RPE where necessary, storage, emergency arrangements and what to do if the planned control is unavailable.

Copying large blocks of technical SDS text can make the assessment harder to use. The objective is not to reproduce the supplier document; it is to convert the relevant information into a safe system for the task.

It should also be reviewed when the product, process, quantity, work location or control method changes, or where experience suggests the existing controls are not effective.

What should you do now?

  • Check that your COSHH register includes substances generated by work as well as purchased products.
  • Confirm SDSs are current, but do not treat them as completed risk assessments.
  • Assess the actual task, exposure routes, duration and people affected.
  • Consider elimination, substitution and engineering controls before relying on PPE.
  • Make the final assessment concise enough for supervisors and workers to use.
  • Review assessments when products, processes, quantities or controls change.

Our professional view

COSHH paperwork becomes most useful when it stops being a chemical filing exercise and starts describing how exposure is actually controlled. The SDS is a source document; the assessment is the employer’s decision-making process.

All Star Safety’s health and safety consultancy service can support businesses developing practical COSHH assessments and site controls, with additional awareness training available through our wider eLearning range.

Does Your Temporary Works Designer Have Enough Information to Design Safely?

Does Your Temporary Works Designer Have Enough Information to Design Safely?

Temporary works design can only be as good as the information it receives. A drawing request that says little more than “design a working platform” or “provide excavation support” leaves important assumptions unresolved. Before design starts, the project needs to define the loads, geometry, sequence, interfaces, constraints and intended use clearly enough for a suitable solution to be developed.

The design problem needs defining before it can be solved

HSE’s temporary works guidance says temporary structures must be designed, installed and maintained to withstand foreseeable loads and used only for the purposes for which they were designed, installed and maintained.

That legal requirement sounds straightforward, but it depends on the design team knowing what those foreseeable loads and intended uses actually are. If plant type, imposed loads, sequence, ground information or interface with permanent works is missing, the designer may be forced to make assumptions that do not reflect what happens on site.

A useful temporary works brief therefore does more than request a drawing. It defines the engineering problem and records the information that the designer is entitled to rely upon.

Start with purpose, geometry and loading

The brief should explain what the temporary works are intended to achieve and for how long. Dimensions, levels, clearances, access requirements and interfaces should be clear enough for the designer to understand the physical problem.

Loads need the same discipline. For a working platform, that might include the actual plant, outrigger or track configuration, operational positions and any delivery vehicles. For propping, the designer needs to understand what is being supported, the sequence of load transfer and when the temporary support can safely be removed.

“Suitable for a crane” is not a design load. “Support the wall” is not a construction sequence. The information should be specific enough that the final design can be checked against the intended operation.

Ground and existing structures can control the design

Temporary works frequently depend on conditions outside the element being designed. Excavation support relies on ground conditions and surcharge. A loading platform may depend on the capacity of the supporting structure. A scaffold can impose loads on façades, slabs or foundations.

Known ground information, buried services, existing structural details and restrictions on where loads can be applied should therefore be supplied where relevant. If reliable information is unavailable, that uncertainty should be made explicit rather than silently replaced with an optimistic assumption.

This is particularly important when permanent works are being used temporarily during construction. The fact that a slab, wall or frame will eventually be strong enough does not automatically mean it can accept the proposed construction load at that stage of the sequence.

The construction sequence belongs in the conversation

HSE notes that a Temporary Works Coordinator may need to advise on build sequence, systems of work and equipment so other activities do not damage or compromise temporary works. Sequence can be central to the design, not simply a site-management issue after the drawing is issued.

Consider a propping arrangement designed on the assumption that load is transferred gradually through a particular sequence. If site operations remove props early, change pour order or introduce extra loading before the structure gains strength, the design may no longer represent the actual condition.

The brief should therefore capture significant erection, loading, alteration and dismantling stages where they influence stability or design.

Changes need to come back through the process

Temporary works often encounter change: plant is substituted, levels alter, access routes move, excavation depth increases or another contractor needs to use the system differently. The safe response is not to assume that a small site change has a small engineering effect.

The TWC should have a process for referring relevant changes back to the designer and obtaining revised or confirmed information before the temporary works are used outside the original design basis. HSE describes the TWC approach as an effective way of coordinating suitable designs, checking and correct erection.

It is important to distinguish this industry management approach from statute. HSE states there is no single specific legal requirement prescribing exactly how temporary works must be organised. The underlying legal duties concern safe design, installation, maintenance and use.

What should you do now?

  • Review the information your organisation normally sends with temporary works design requests.
  • State the intended purpose, geometry, duration and relevant construction stages.
  • Define real loads and plant configurations rather than generic descriptions.
  • Provide available ground, structural and service information where it affects the design.
  • Record significant assumptions and information gaps.
  • Define how site changes are referred back for design review.
  • Make sure the TWC has authority to stop use where the design basis has not been satisfied.

Our professional view

A temporary works register can tell you what designs exist, but it does not prove the designers were given the right problem to solve. A strong process starts earlier, with a brief that connects design calculations to the actual method, plant, sequence and site constraints.

For teams developing their understanding of the process, All Star Safety provides CITB Temporary Works General Awareness eLearning, while our consultancy service can assist with practical temporary works coordination and review.

Could Your Excavation Collapse Before Anyone Sees the Warning Signs?

Could Your Excavation Collapse Before Anyone Sees the Warning Signs?

A fatal trench collapse and a recent HSE prosecution are a reminder that excavation safety depends on decisions made before anyone enters the ground. Soil type, spoil placement, plant loading, nearby structures, temporary support and competent inspection all need to be considered before movement, cracking or collapse gives a visible warning.

A fatal trench collapse brought familiar failures back into focus

On 9 September 2026, HSE reported the sentencing of two companies and an individual following the death of 33-year-old Gheorghita Arsene, who was buried when the sides of a deep trench collapsed during pipework at Banstead in Surrey. HSE said the excavation had no support and excavated soil had been deposited immediately beside the edge.

Appledorn Developments Ltd was fined £500,000. Subcontractor T Vaughan Ltd was fined £650,000 plus £40,000 costs. A contracts manager received a 10-month suspended prison sentence and 150 hours of unpaid work after pleading guilty to an offence under section 7 of the Health and Safety at Work etc. Act 1974.

The value of the case is not in treating those penalties as a benchmark. It is in recognising the underlying issues: unsupported ground, surcharge at the edge and management failures that allowed people to work in a dangerous excavation.

The duty is to prevent collapse, not react to it

Regulation 22 of CDM 2015 requires suitable and sufficient steps to prevent danger from the collapse of an excavation and addresses the effect of materials and equipment placed near an excavation. The objective is prevention rather than waiting for obvious movement before taking action.

That does not mean every excavation needs the same support system. Depending on depth, ground conditions, loading and geometry, the solution might involve shoring, trench boxes, another designed support system or battering the sides to a suitable angle. The method needs to suit the actual conditions.

HSE’s excavation guidance warns that no ground should be relied upon to stand unsupported in all circumstances. It also notes that a cubic metre of soil can weigh more than 1.5 tonnes, which helps explain why even a localised collapse can be fatal.

Spoil and plant can change the ground loading

Excavated material is not harmless simply because it has been removed from the trench. Spoil placed close to the edge creates surcharge and can increase the likelihood of collapse. Excavators, dumpers, telehandlers and delivery vehicles can add further loading and vibration.

The safe stand-off distance should be determined from the excavation, ground conditions and equipment involved. It should not be an arbitrary site rule that is copied between projects without considering the real situation.

Nearby foundations, scaffold bases, services, retaining structures and temporary works also matter. Digging can remove support that another structure relies upon. A trench that looks straightforward in open ground may become a more significant engineering problem when it runs beside an existing building or loaded area.

Excavation support is often temporary works

HSE identifies excavation shoring as temporary works. That means it needs to be planned and managed as an engineered solution where the risk requires it, with suitable design and checking arrangements rather than improvised support selected after excavation has already progressed.

For more complex excavations, the temporary works process should define the design requirement, anticipated loads, sequence, interfaces and any limits on plant or material near the edge. The Temporary Works Coordinator needs enough information and authority to control the process, but the role title itself does not make an unsafe excavation safe.

Businesses needing a refresher on these principles can also use All Star Safety’s CITB Temporary Works General Awareness eLearning as an introduction to temporary works management.

Safe access and services still need attention

Collapse prevention is central, but it is only one part of excavation safety. Buried services should be identified and managed before digging starts, with work planned around the information available and safe digging practices used where services may be present.

People also need safe access and egress. Ladders, where used, need to be suitable, secured and positioned so people can get in and out without creating another hazard. Edge protection, water ingress, hazardous atmospheres and the possibility of materials falling into the excavation may also need control.

A trench box does not compensate for an insecure access ladder, a dumper operating too close to the edge or a failure to identify buried electricity or gas services.

Inspection is a live control measure

Regulation 24 of CDM 2015 sets inspection requirements for excavations where the relevant protective measures are needed. HSE explains that inspections should take place at the start of each working shift and after events that could affect stability, as well as following a fall of rock or earth.

The purpose is not another signature for the file. The competent person needs to recognise changes in the ground, supports, loading, water or surrounding activity and have enough authority to stop work until a defect or concern is resolved.

What should you do now?

  • Confirm who is responsible for planning, supervision and inspection of each live excavation.
  • Assess ground conditions and nearby structures before excavation starts.
  • Decide the support, trench-box or battering arrangement before people enter.
  • Control spoil, materials and plant loading near the edge.
  • Locate buried services and use suitable digging methods.
  • Provide secure access, egress and edge protection where required.
  • Inspect at the legally required times and after anything that could affect stability.

Excavations should be treated as changing temporary conditions rather than holes that have already been “made safe”. All Star Safety’s consultancy service can support contractors reviewing excavation arrangements, temporary works interfaces and site controls.

Is Your Health Surveillance Actually Risk-Based?

Is Your Health Surveillance Actually Risk-Based?

Health surveillance is often confused with general health screening, wellbeing checks or an annual medical. In construction, that distinction matters because some surveillance is a legal requirement where particular occupational health risks remain. The starting point should be the work and exposure, not a standard package of tests offered to everybody.

Occupational Health Awareness Week is a useful prompt to check the system

IOSH used Occupational Health Awareness Week, running from 21 to 27 September 2026, to encourage employers to put healthier work alongside safety management. That is particularly relevant to construction, where noise, vibration, dusts, hazardous substances and other exposures can cause harm slowly and may not produce an obvious incident at the time.

HSE’s construction health-surveillance guidance describes surveillance as a risk-based system of ongoing health checks used where work exposures may cause harm. It distinguishes legally required surveillance from optional wellbeing or general health checks.

This matters commercially as well as legally. Paying for broad health screening does not necessarily discharge a specific duty to provide suitable health surveillance for workers exposed to a relevant occupational hazard.

Start with the risk assessment, not the medical provider

HSE says health surveillance is required in specific circumstances where residual risk remains despite controls and workers are likely to be exposed to risks such as noise, vibration or substances hazardous to health. The need therefore comes from the risk assessment and exposure profile.

A useful review starts by identifying who actually uses vibrating tools, who works in noisy areas, who may be exposed to respirable crystalline silica, sensitising substances or other hazardous agents, and what controls are already in place. The next question is whether surveillance is required for those people and that exposure.

That approach avoids two common errors: putting everyone through the same tests regardless of exposure, or assuming that good engineering controls remove the need to consider surveillance altogether.

Health surveillance is not exposure monitoring

HSE makes an important distinction between monitoring the workplace exposure and monitoring the worker’s health. Exposure monitoring might measure airborne dust, noise levels or vibration exposure. Health surveillance is designed to detect early signs of work-related ill health and to test whether the wider control system is working.

Both can be necessary, but one does not replace the other. A dust sample that shows exposure is well controlled does not tell you whether an individual has developed symptoms. Equally, an annual health questionnaire cannot tell you whether the extraction system is actually controlling the airborne concentration during a particular task.

Where specialist advice is needed, HSE says health-surveillance schemes should normally be set up with input from a competent occupational-health professional. Certain forms of medical surveillance have additional legal requirements.

Vibration shows why the detail matters

Construction workers using breakers, grinders, drills, compactors, scabblers and other vibrating equipment can be at risk of hand-arm vibration syndrome. Under the Control of Vibration at Work Regulations, exposure must first be prevented or reduced; health surveillance is not a substitute for controlling the vibration.

HSE’s construction vibration guidance says appropriate health surveillance is needed where workers are exposed above the Exposure Action Value or are otherwise considered at risk. Findings should then feed back into the risk-control process.

That feedback loop is critical. If surveillance identifies symptoms, management should review the person’s exposure, tools, work methods, maintenance, task duration and controls rather than simply filing the health-surveillance result.

Dust, noise and skin exposure need their own logic

The same principle applies across other construction health risks. Noise surveillance is linked to the risk of noise-induced hearing loss. Surveillance for hazardous substances may be appropriate for occupational asthma, dermatitis or exposure to respirable crystalline silica depending on the circumstances.

For silica, HSE states that health surveillance must be provided where workers are regularly exposed to respirable crystalline silica and there is a reasonable likelihood that silicosis may develop. The assessment needs to reflect actual activities such as cutting, grinding, drilling or stonework rather than simply the job title.

Different hazards may require different techniques and frequencies. A generic “annual medical” should therefore not be assumed to cover every statutory surveillance need.

What should you do now?

  • Map the significant occupational-health exposures in your current workforce.
  • Check whether existing risk assessments identify the need for health surveillance.
  • Separate legally required surveillance from general wellbeing or voluntary health screening.
  • Confirm the surveillance method is appropriate to the specific hazard.
  • Use competent occupational-health input where required.
  • Review how findings are fed back into exposure controls and work planning.
  • Keep health information confidential and restrict access appropriately.

Our professional view

A mature health-management system does not start by asking which medical package to buy. It starts by understanding the hazards created by the work, controlling them as far as reasonably practicable and then deciding what surveillance is required for the residual risk.

That is also why surveillance should be treated as part of risk management rather than an HR benefit. Its value is in identifying early harm and prompting corrective action before exposure causes more serious or irreversible damage.

All Star Safety’s health and safety consultancy service can support businesses reviewing occupational-health risk assessments, exposure controls and the management arrangements that sit around health-surveillance programmes.