Short answer: no. Moving, capping, cutting or disconnecting gas pipework, appliances or flues is gas work. Under the Gas Safety (Installation and Use) Regulations 1998 it must be done by a competent engineer from a Gas Safe registered business, registered for that type of work. A builder who finds gas services in the way should stop, and the programme should be changed around a specialist alteration.
Refurbishment work often exposes services that were not obvious at tender stage. When gas pipework, appliances or flues conflict with an extension, alteration or strip-out, they are easy to treat as just another obstruction. That is where things go wrong.
Why is HSE warning about illegal gas work?
During Gas Safety Week (14 to 20 September 2026), HSE reported that 17 people had been convicted for carrying out gas work illegally since the beginning of 2025. Unregistered gas work can lead to leaks, fires, explosions and carbon monoxide poisoning.
HSE’s September 2026 warning matters to refurbishment contractors because gas risks can arise during ordinary building work, even when the job was never described as a gas installation.
A separate HSE prosecution reported in August involved an extension built over existing gas service pipework and around a boiler flue, without the required alterations being made. The installation was later classified as immediately dangerous.
What does Regulation 3 require?
Regulation 3 of the Gas Safety (Installation and Use) Regulations 1998 requires gas work to be carried out by competent people. Where a business does the work, it must be a member of the class of persons approved by HSE, which in practice means the Gas Safe Register.
Registration is not a blanket licence. The engineer should be competent and registered for the particular type of gas work involved. For a general builder, the rule is simple: if the gas installation needs changing, it is not your trade’s job.
How can building work create a gas risk?
It goes well beyond boiler installation. Excavation can expose service pipes. Structural alterations can affect flue routes. Kitchen or plant-room changes can clash with existing pipework. New walls can enclose equipment, and demolition can remove supports or ventilation that formed part of the original safe installation.
This is a CDM 2015 issue as much as a gas one. Foreseeable risks should be planned and coordinated, not left for workers to solve at the point of work. Existing-services information, surveys, pre-construction information and site briefings all help find the problem early. If the method changes once a service is found, the risk assessment needs reviewing too.
Who controls the interface on site?
On projects with several contractors, the principal contractor must plan, manage, monitor and coordinate the construction phase. That does not make them a gas specialist, but they should decide who is authorised to do the gas work and how it fits the sequence. We cover this in more detail in Can a principal contractor leave safety to subcontractors?
Make the boundary explicit in the RAMS and construction phase plan. General operatives may expose an area carefully under an agreed method, but any intervention in the gas installation itself belongs to the registered engineer, with isolation, testing and handover clearly defined.
Check registration as well. HSE has prosecuted cases where businesses relied on people who claimed to be qualified but were not. Looking up the engineer or business on the Gas Safe Register takes a minute and should be done before the work starts.
What should happen when gas services are in the way?
Stop the affected activity and establish what the service is, whether it is live and what change is actually needed. Do not cut, cap, bend, reroute or disconnect pipework to keep progress going.
Give the gas engineer enough information to understand the finished building, not just today’s obstruction. Flue routes, ventilation, maintenance access, protection from damage and new structural or fire-resisting elements may all need considering.
What should you do now?
- Identify existing gas services, appliances and flues during pre-start planning.
- Make the boundary between general building work and gas work clear in RAMS and briefings.
- Do not let builders or other trades move, disconnect or modify gas installations.
- Check the engineer or business on the Gas Safe Register before work starts.
- Coordinate isolation, alteration, testing and reinstatement with the programme.
- Stop and reassess when unexpected pipework or flues are found.
- Record service changes so the handover information matches what was actually left in place.
Our professional view
Most gas-safety failures we hear about on refurbishment jobs start as coordination failures, not deliberate law-breaking. A service is found late, the programme is tight and someone makes a quick alteration to keep moving. Clear stop-work boundaries and early specialist involvement are far more reliable than expecting operatives to judge the limit themselves.
All Star Safety Ltd’s CDM 2015 Awareness course covers dutyholder responsibilities and construction-phase coordination. For supervisors who manage these interfaces day to day, the Level 4 NVQ in Construction Site Supervision builds and evidences that competence on your own site. If you would like a second pair of eyes on your RAMS or construction phase plan, talk to our health and safety consultancy team on 01473 561402.